Commercial gutter-clearance case study

Commercial gutter clearance at Suffolk Park, Bury St Edmunds

Approximately 2.5 kilometres of industrial guttering cleared across a live distribution site, with no disruption to normal operations.

2.5km

Approximate total gutter length

12 gutter runs

10 valleys and two end gutters

Four-day project

Up to four operatives

Live distribution site

No disruption to operations

Planned maintenance

Before and after nesting season

Project overview

A planned clearance on an industrial scale

Pro Clean Xtreme completed a planned commercial gutter-clearance project at a large distribution building at Suffolk Park, Bury St Edmunds, occupied by Skechers and Bleckmann.

The work had been planned since February as part of a twice-yearly maintenance programme: one clearance before nesting season and another afterwards. This four-day visit was the post-nesting-season clearance.

Location

Suffolk Park, Bury St Edmunds

Property

Large distribution building

Service

Commercial gutter clearance

Duration

Four working days

Access

Own 21m tracked cherry picker

Evidence

Photos and end-of-job survey

The twelve runs and the two issues recorded in the end-of-job survey.

The scale

Approximately 2.5 kilometres of guttering

The roof contains 12 full-length gutter runs: 10 internal valley gutters and two end gutters.

Each run measures approximately 214 metres. Across all 12, that gives an estimated combined gutter length of 2,564 metres—around 2.5 kilometres.

12 × 214m

Ten internal valleys and two end gutters

The aerial plan gave the team a clear reference for recording progress and pinpointing any issues discovered.

The scale

Planned around normal operations

The distribution centre remained fully operational throughout the project, with no disruption to normal activities.

Pro Clean Xtreme’s own 21m tracked cherry picker was used to access the roof. Once on the roof, the team connected to the existing Mansafe lines wherever required while progressing along the gutters.

The work followed a site-specific RAMS. Because the gutters contained bird fouling, the team used respiratory protection, disposable coveralls and gloves.

Controlled working zones
Vehicle routes protected
Cherry-picker drop zone
Cones and physical barriers
Mansafe lines used where needed
Suitable PPE and RPE
How the work was completed

Manual clearance with direct outlet checks

The gutters were cleared manually by hand rather than using a gutter vacuum or blower. This gave the team direct access to the gutter channels and outlets.

Establish the working zones

Cones and barriers separated the work, vehicle and cherry-picker drop zones.

Access the roof

The team used the company’s own 21m tracked cherry picker, then the existing Mansafe system where required.

Clear each gutter by hand

Feathers, bird fouling and general debris were removed manually and placed into bags.

Remove the outlet covers

The covers were unbolted so trapped material could be removed and the accessible outlets checked.

Transfer waste from the roof

Bagged material was sent down the enclosed chute directly into the skip below.

Photograph and report

Conditions, progress, completed runs and visible issues were recorded for the end-of-job survey.

Before and after

Heavy debris removed from the valley gutters

Genuine project photographs show the condition found and a representative gutter after manual clearance.

After
After
Controlled waste removal

From roof level directly into the skip

The feathers, bird fouling and general debris were cleared manually and placed into bags at roof level.

The bags were then sent down a temporary enclosed chute directly into the skip below. This kept the removed waste contained and allowed it to be transferred safely from the roof without disrupting the operational distribution site.

Bagged gutter waste transferred safely from roof level into the skip below.
Issues identified

Visible defects were marked and reported

The clearance exposed two separate issues for the building-management team to review.

Run 2

Gutter-lining damage

Visible damage was identified in the gutter lining. Its position was photographed and marked on the annotated roof plan for further review.

Run 3

Persistent blocked outlet

The second outlet from the bottom remained blocked. Visible debris was removed and the outlet was plunged, but standing water remained, indicating a restriction beyond the accessible section.

Clear reporting: the agreed clearance was completed and the two separate issues were included in the end-of-job survey. Further information can be supplied if required.
The completed result

All 12 runs cleared and documented

All 12 commercial gutter runs were manually cleared. The accumulated feathers, bird fouling and general debris were bagged and removed for skip disposal.

All 12 gutter runs manually cleared
All outlet covers opened and trapped debris removed
All outlets free-flowing apart from the persistent Run 3 blockage
Run 2 damage and Run 3 blockage photographed and marked
End-of-job survey supplied with photographic evidence
Normal site operations continued without disruption
Commercial gutter-clearance questions

Useful information for site managers

How often should commercial gutters be cleared?

The appropriate frequency depends on the site, surrounding environment, roof design and previous findings. At this distribution building, a planned clearance takes place before nesting season and again afterwards.

Subject to a suitable site assessment and safe working plan, work can be arranged around normal operations. This four-day project was completed while the distribution centre remained operational and without disruption.

Access is assessed for each site. For this project, our own 21m tracked cherry picker provided roof access and the existing Mansafe lines were used where required.

Where included in the agreed scope, we can provide before, during and after photographs, an annotated site plan, details of the work completed and any visible issues identified.

Commercial gutter clearance

Need a planned gutter programme for your site?

Send the site address, photographs and any known access restrictions for an initial assessment.

Call Now Button